COAL ENGINEERING ›› 2014, Vol. 46 ›› Issue (1): 22-23.doi: 10.11799/ce201401007

Previous Articles     Next Articles

Pole Adjustment of 10kV Overhead Line,East Ventilation Shaft of a Coal Mine

  

  • Received:2013-02-28 Revised:2013-06-18 Online:2014-01-10 Published:2014-01-10

Abstract:

This paper presents briefly the pole adjustment scheme and measures when the 10kV overhead line of an east ventilation shaft strides over coal mining subsidence area,and some Suggestions are given in the last.

Key words: Subsidence Area, Pole Adjustment