煤炭工程 ›› 2015, Vol. 47 ›› Issue (6): 70-72.doi: 10.11799/ce201506023

• 生产技术 • 上一篇    下一篇

母杜柴登矿首采工作面疏干水量计算研究

刘基   

  1. 中煤科工集团西安研究院
  • 收稿日期:2014-05-17 修回日期:2014-08-12 出版日期:2015-06-10 发布日期:2015-06-12
  • 通讯作者: 刘基 E-mail:g73018606@126.com

Study on the calculation of the drainage water yield in the first mining face

  • Received:2014-05-17 Revised:2014-08-12 Online:2015-06-10 Published:2015-06-12

摘要: 分析了母杜柴登首采工作面主要充水水源为顶板砂岩含水层,通过放水试验获取含水层的渗透系数,在此基础上,采用干扰井群的叠加原理计算了首采工作面内部的疏干水量,并根据计算确定了顶板疏放水钻场的最终布置方式,为计算工作面内部疏干水量提供了一种新的思路。

关键词: 工作面疏水, 放水试验, 渗透系数, 疏干水量, 顶板疏放水

Abstract: The water filling source is the sandstone aquifer on the roof in the mining face in muduchaideng coal mine which is analyzed in this paper. The permeability coefficient is obtained by the underground dewatering test. On this basis, the drainage water yield in the first mining face is calculated by the principle of superposition of the interference well group. According to the result, the final arrangement of the the roof water drainage drilling field is determined. It provides a new way of calculating the drainage water yield in the first mining face and a valuable reference value for calculating the drainage water yield of the surrounding mine.

Key words: the interference well group, the principle of superposition, the first mining face, the drainage water yield

中图分类号: