煤炭工程 ›› 2022, Vol. 54 ›› Issue (7): 38-43.doi: 10.11799/ce202207008

• 施工技术 • 上一篇    下一篇

立井煤矿深埋长距离岩巷全断面硬岩掘进机施工技术研究

何杰,崔千里,付书俊,范军平,李育朋   

  1. 1. 天地科技股份有限公司
    2. 中煤科工集团天地公司开采设计事业部
    3. 山西省阳煤集团
  • 收稿日期:2021-10-25 修回日期:2022-01-13 出版日期:2022-07-15 发布日期:2022-07-20
  • 通讯作者: 何杰 E-mail:13313559095@163.com

Research on construction technology of full section Hard rock Machine for deep buried long distance rock roadway in vertical coal Mine

  • Received:2021-10-25 Revised:2022-01-13 Online:2022-07-15 Published:2022-07-20

摘要: 针对我国煤矿岩巷掘锚失衡、成巷效率低问题,采用理论分析、仿真模拟及现场试验的方法,开展了煤矿巷道全断面硬岩掘进机盾构法施工适应性及系统匹配性分析,提出了影响立井煤矿巷道盾构法施工效率的四个关键因素,包括设备出入立井、快速组装与运输、轨迹控制及快速支护。结合矿井现有条件,设计了井下大型硐室设备组装与拆卸平台,优化了施工工艺,形成了集掘、支、装、转、运、喷多工序协调统一的盾构施工技术体系。研究成果在阳泉新景煤矿岩巷掘进中首次成功应用,实现了最高月进尺608m,最高日进尺31.5m,创造了煤矿单次掘进、一次成巷3490m的水平,大幅提高了岩巷成巷效率,缩短了矿井准备周期,取得了显著技术经济效益。

关键词: 深埋长距离巷道, 岩巷掘进, 盾构法施工, 一次成巷

Abstract: In view of the problems of unbalance of excavation-anchor and low efficiency of roadway formation in coal mine, by means of theoretical analysis, simulation and field test, the adaptability of shield tunneling and matching of construction system of full-section hard rock machine in coal mine are analyzed. Four aspects of problems affecting the construction efficiency of shield tunneling in vertical coal mine are proposed. It includes shield machine access to vertical shaft, equipment rapid assembly and transportation technology, shield machine trajectory control and rapid support. Combined with the existing conditions of the mine, the shield equipment assembly and disassembly platform of the underground large chamber was designed, the construction technology and labor organization management were optimized, and the shield construction technology system with multi-process coordination and unity of digging, supporting, assembling, transferring, transporting and spraying was formed. The research results were applied for the first time in rock roadway of Yangquan high gas vertical shaft coal mine, which realized the highest monthly and daily footage of rock roadway 608m and 31.5m, and created the level of rock roadway forming 3490m in a single tunneling and a single tunnel forming, improved the efficiency of rock roadway forming, shortened the mine preparation period, and achieved significant technical and economic benefits.

中图分类号: