Research on coalescence of last cutting stope and supporting technology of super height mining face

  • Received:2022-11-30 Revised:2023-09-15 Online:2023-06-20 Published:2025-01-08

摘要:

主回撤通道围岩控制质量的好坏直接影响工作面撤出效率以及矿井安全生产。为了进一步优化回撤通道支护方案, 提高支护效率,以神东矿区大柳塔矿52501主回撤通道为例,采用FLAC3D数值模拟方法,对末采阶段回撤通道围岩塑性破坏区演化规律开展研究,给出了末采阶段主动支护的作用范围及效果, 提出主动支护优化的可行性。进一步对现有回撤通道支护方案进行优化,并在相邻工作面主回撤通道进行应用。研究结果表明:优化后巷道正帮和副帮变形量分别为302mm和73mm,较原方案变形量增加了5.9%和7.3%; 顶板的变形量为236mm,较原方案增加了4.8%。优化方案支护参数仍然可使主回撤通道保持稳定,并且支护强度适度降低,使得成本大幅下降,效率提高。

关键词: 超大采高工作面 , 主回撤通道 , 支护优化 , 围岩变形量

Abstract:

The support of the surrounding rock of the main equipment remove gateway is an important problem that must be solved in the large mining face with the multi channel moving technology of the auxiliary alley. It's quality directly affects the removal efficiency of the working face and the safe production of the coal mine. In order to further optimize the retracting channel support scheme and improve the quality of support. Take Shendong Daliuta coal mine 52501 main equipment remove gateway as an example. Using the FLAC3D numerical simulation method. Research on the existing retracting channel support scheme. The research results are expected to be applied to the next main equipment remove gateway in the next working face. The results of the study show that, after the optimization, the deformation of the positive buttock and negative buttock of the tunnel is 302mm and 73mm. An increase of 5.9% and 7.3% compared with the existing schemes. The deformation of the roof is 236mm. More than 4.8% of the existing schemes have been increased. The support parameters of the optimized scheme can keep the main retracting channel stable.