煤炭工程 ›› 2024, Vol. 56 ›› Issue (12): 55-59.doi: 10.11799/ce202412009

• 施工技术 • 上一篇    下一篇

斜井长距离安全高效揭强突出煤层关键技术研究与应用

李良山   

  1. 中煤华晋集团晋城能源有限公司
  • 收稿日期:2024-02-01 修回日期:2024-10-07 出版日期:2024-12-20 发布日期:2025-01-08
  • 通讯作者: 李良山 E-mail:502386262@qq.com

Research and practice on safe and efficient technology for inclined shafts passing through strong outburst coal seam with long distances

  • Received:2024-02-01 Revised:2024-10-07 Online:2024-12-20 Published:2025-01-08

摘要: 相对于普通石门揭煤,斜井长距离揭煤风险高、难度大。为确保里必煤矿主斜井安全高效穿过突出煤层,根据地质探测、支护设计及揭煤区域3#煤层实测瓦斯参数,分析了斜井长距离揭煤的技术难点,提出了安全揭煤技术对策。采用导硐布孔,提出大孔径增孔深、多“掏穴”、下套管、高负压、气举反循环排渣、固化截抽等“六位一体”综合强化抽采技术体系,显著提高了钻孔施工质量,解决了斜井长距离揭强突出煤层高效抽采难题,有效控制了炮后瓦斯涌出量。采用斜井竖向一次性揭开强突出煤层方法,显著增加了一次揭煤范围|斜井轮廓线密眼切槽预处理方法,解决了过煤段顶板及成型控制难题。实践表明,从揭开3#煤层至穿过煤层法距3 m,历时36 d,揭煤过程中炮后工作面瓦斯最大0.68%,回风流瓦斯最大0.36%,确保了斜井揭煤作业安全,为类似条件斜井长距离揭煤提供了重要的借鉴意义。

关键词: 导硐布孔, 掏穴扩孔, 截流抽采, 垂直钻孔爆破, 密孔切槽

Abstract: Compared with ordinary stone gate uncovering coal, long-distance coal uncovering in inclined shaft is high risk and difficult. In order to ensure that the shaft safely and efficiently passes through the outburst coal seam, the technical difficulties for long-distance coal uncovering of inclined shafts were analyzed, and safety measures for uncovering outburst coal seam proposed, based on the geological exploration results, support design and measured gas parameters of the coal seam No.3 in the coal uncovering area. By using the guide tunnel hole layout, a comprehensive enhanced extraction technology system of "six in one", such as increasing the hole depth with large aperture, multiple " burrowing holes ", casing down, high negative pressure, gas lift reverse circulation slag cleaning, and curing intercept extracting, has been put forward, which significantly improves the construction quality of drilling, solves the problem of efficient extraction of long distance exposed strong outburst coal seam in inclined shafts, and effectively controls the amount of gas emission after exploding.The method of vertical uncovering strong outburst coal seam at one time in inclined shaft is adopted, which significantly increases the range of uncovering coal at one time. The problem of roof and forming control in coal passing section is solved by the method of dense hole slotting for contour lines pretreatment for inclined shaft contour. It took 36 days from uncovering the coal seam No. 3 to passing through the coal seam at the vertical distance of 3 m. The maximum gas concentration in the working face after the blasting was 0.68%, and the maximum gas concentration in the return air flow was 0.36% during uncovering the coal. The operation of inclined shafts uncovering coal was successfully carried out, which provides important reference significance for long-distance uncovering outburst coal seams under similar conditions.