煤炭工程 ›› 2009, Vol. ›› Issue (11): 0-0.

• 施工技术 •    

综采搬家换面关键环节的组织及施工

高运增   

  1. 北京天地华泰采矿工程技术有限公司
  • 收稿日期:2009-07-26 修回日期:2009-09-07 出版日期:2009-11-06 发布日期:2009-11-10
  • 通讯作者: 高运增 E-mail:yunzengbj@163.com

The organization and construction of the key process in changing totally mechanized working face

  • Received:2009-07-26 Revised:2009-09-07 Online:2009-11-06 Published:2009-11-10

摘要: 综采设备搬家换面是综合机械化开采矿井组织管理最为复杂、危险性最高的一个重要生产环节。该环节对组织者及施工人员的技术要求较高,需要多部门、多工种的密切配合。笔者结合黑岱沟煤矿生产实践经验,重点介绍了搬家换面过程中液压支架撤出、设备运输、液压支架安装等关键环节的组织及施工方案,对鄂尔多斯地区矿井综采搬家换面工作将起到一定的参考作用。

关键词: 搬家换面, 安全快捷, 关键环节

Abstract: Moving the equipments from the finished totally mechanized working face to an new one is the most complex and the highest risk major process in the totally mechanized coal mining. The process requires the organizers and the workers for higher skills, and the process requires the department and workers in close collaboration with. With the practical experience of Heidaigou coal-mine, the writer will introduce the organization and construction of the key process, such as moving hydraulic supports out, transporting equipments, installing hydraulic support. It will be a reference to the work of moving the equipments from the finished working face to a new working face in Eerduosi.

Key words: Changing working face, fast and safe, key process