COAL ENGINEERING ›› 2014, Vol. 46 ›› Issue (12): 50-52.doi: 10.11799/ce201412017

Previous Articles     Next Articles

The Breaking Pile Processing Scheme for Bridge Bored Piles

  

  • Received:2013-11-13 Revised:2014-01-22 Online:2014-12-12 Published:2014-12-10

Abstract:

With the rapid development of engineering construction in our country, bored piles as a foundation type are widely used in Highway Bridges and other engineering practices, and achieved good effect because of its characteristics of widely adaptability, moderate cost, simple construction. bored piles belong to underground hidden construction work, breaking piles often happen in practices, the paper elaborated the processing scheme for breaking pile as to the Kang Gou 1# bridge, this contents can provide reference for the breaking pile processing.

Key words: bridge, bored piles, Breaking pile, processing scheme

CLC Number: