煤炭工程 ›› 2014, Vol. 46 ›› Issue (4): 62-63.doi: 10.11799/ce201404022

• 生产技术 • 上一篇    下一篇

选煤厂主洗车间梁板过大振动响应的测试及分析

郭昭胜1,高志辉2   

  1. 1. 太原理工大学建筑与土木工程学院
    2. 北方工程设计研究院有限公司
  • 收稿日期:2013-11-25 修回日期:2013-12-27 出版日期:2014-04-11 发布日期:2014-04-10
  • 通讯作者: 郭昭胜 E-mail:13934511792@163.com

Test and analysis of the excessive vibration response about beam-plates system of some coal preparation plant main workshop

  • Received:2013-11-25 Revised:2013-12-27 Online:2014-04-11 Published:2014-04-10

摘要:

某选煤厂主洗车间经年处理120万吨设备改造后,引发了离心机与振动筛所在楼板的过大竖向振动反应。分别对标高5.3 m及标高13.8m楼板振动响应进行了测试,得到了振动设备的扰频、测点的竖向振动响应信号曲线及位移振幅值。经分析指出梁板体系竖向刚度相对较弱及强迫共振是导致楼面较大振动响应的根本原因,讨论了已有加固措施的不足之处,提出新的减振加固思路。

关键词: 楼板振动, 现场测试, 共振, 减振加固

Abstract:

In some coal preparation plant main workshop, 1.2 million tons equipment reformation was completed,The excessive vibration behavior of beam-plates system caused by equipment reformation were tested. The disturbing frequency of vibrating equipment and response of floor vibration were obtained. According to the spot test results,the main cause of excessive vibration of floor is forced resonance, in addition, relatively small vertical stiffness of floor is a reason. The shortcoming of existing strengthening measures was analysis, and then the new vibration reduction treatment scheme was proposed.

Key words: floor vibration, spot testing, resonance, vibration reduction and strengthening