园子沟矿井建设总体方案优化设计

杨怀敏,滕鑫麟,魏高巍   

  1. 河北工程大学
  • 收稿日期:2013-06-25 修回日期:2013-10-08 出版日期:2014-08-11 发布日期:2014-08-10
  • 通讯作者: 杨怀敏 E-mail:250599217@qq.com

General construction scheme optimization design of the mine Yuan Zigou

  • Received:2013-06-25 Revised:2013-10-08 Online:2014-08-11 Published:2014-08-10

摘要:

矿井建设总体方案设计是矿井施工组织设计的重要环节,以施工方案优化为重点,通过施工方案的优化达到缩短建设工期、提高经济效益的目的。本文围绕提升和通风安全这两个重要系统,以三条井筒交替装备顺序为核心,对园子沟矿井的几种总体建设方案进行了对比,最后得出了最优方案。

Abstract:

This essay will explore the subject of construction organization in relation to the overall plan of mine what is a significant process. While shrink the project time –limit and enhance economic performance as a target, which put emphasis on construction project optimization. It looks at the use of the two systems within the industry and explores the importance of them for ascension and ventilation safety specifically within the context of alternating with three wellbore equipment order. This article will use as a case study a number of mining projects inYuanZiGou and though contrastive analysis will aim to offer optimal solutions to the problem of scheme optimization for time in relation to this example.

Key words: Mine construction, wellbore equipment, scheme optimization