顺和煤矿主井井筒基岩段大段高预注浆防治水设计与施工

解三健,刘兴彦,赵燕青,赵逢进   

  1. 永城煤电控股集团有限公司
  • 收稿日期:2015-04-09 修回日期:2015-05-01 出版日期:2016-05-10 发布日期:2016-06-15
  • 通讯作者: 解三健 E-mail:sanjian_03@163.com

Design and Construction on Large segment Section Face Pre-Grouting and Water Prevention and Control for Water-blocking in the Main Shaft bedrock segment of Shunhe Mine

  • Received:2015-04-09 Revised:2015-05-01 Online:2016-05-10 Published:2016-06-15

摘要: 为保证安全高效通过永夏矿区标志含水层K6砂岩,在施工顺和煤矿主井井筒-565~-705m基岩段时,采用工作面大段高预注浆施工方案。注浆结束后,单孔涌水量减少到了1.01m3/h以下,取得了显著的效果,为井筒掘砌施工创造了良好条件,使井筒得以安全顺利落底。

关键词: 基岩段, 大段高, 工作面预注浆, 地面注浆站

Abstract: To ensure through the sign K6 sandstone aquifer of Yongxia mine security and efficient, in construction the Main Shaft -565m~-705m bedrock segment of Shunhe Mine , we applyed face large section Pre-Grouting for water-blocking ,in the end ,the hole water inflow reduced to 1.01m3/h or less, achieved remarkable results, create favorable conditions for driving and masonry shaft , wellbore to be safe and smooth off the bottom.