Application research of steel box girder bridge in overpass engineering of open pit Mine

  • Received:2022-03-23 Revised:2022-07-05 Online:2022-11-15 Published:2023-03-09

摘要: 为了避免运输系统形成平面交叉带来的安全隐患,大多露天矿采取独立的剥离运输系统及原煤运输系统。针对设置独立剥离及原煤运输系统导致剥离运距急剧增大,运输成本居高不下的问题,利用钢箱梁桥施工便捷、材料利用效率高及模块化等特点,通过设置立交设施提高整体运输效率。结合钢箱梁桥在胜利西二号露天矿立交工程中的应用,介绍了其桥型布置、结构分析、效益测算方法,证明了钢箱梁桥在露天煤矿立交工程中应用技术可行、效益显著,对解决类似露天矿交叉运输问题具有一定借鉴意义。

关键词: 露天煤矿, 运输系统, 装配式工业建筑, 结构验算, 有限元

Abstract: At present, there are cross transportation problems in many open-pit mine transportation systems in China, such as Pingshuo East open-pit mine, Pingshuo Anjialing Mine, Xiwan open-pit mine and Hequ open-pit mine. In order to avoid the potential safety hazard caused by plane crossing of transportation system, most open-pit mines adopt independent stripping transportation system and raw coal transportation system. However, the independent transportation system directly leads to the sharp increase of stripping transportation distance and high transportation cost, which seriously affects the economic benefits of open-pit mines. Years of practice in traffic management system has proved that proper setting of interchange facilities is the most effective solution to improve the overall transport efficiency. This paper introduces the application of steel box girder bridge in the overpass project of Shengli West No.2 open-pit mine. Through the study of bridge layout, structure analysis and benefit calculation, it is proved that the application of steel box girder bridge in the overpass project of Shengli West No.2 open-pit mine is technically feasible and the economic benefit is obvious. It can be used as a reference for solving similar cross transport problems in open-pit mines.