摘要: 为了合理确定胜利西二号露天煤矿3号原煤半固定破碎站移设时间节点及移设步距,基于露天开采原理,依据该矿采区转向方式,编制了2023—2027年开采进度计划。通过对各年度采场、排土场工程位置发展情况进行推演,分析确定了3号破碎站合适的移设时间节点及可行的移设路径。依据采剥程序规划,测算了3号原煤破碎站不同移设步距时,开采块段内原煤资源量、原煤汽车运距、胶带运距、破碎站服务年限等指标。结合移设费用补偿法、加权成本最小法确定了3号破碎站经济合理移设步距。结果表明:3号破碎站移设时间节点为2026年4月份前,移设路径为沿采场东帮胶带运输系统布置方向进行回撤,移设距离为1200 m。此时移设费用得到补偿,加权成本最小,经济效果良好。

关键词: 露天矿, 季节性剥离, 半连续工艺, 半固定破碎站, 移设步距

Abstract: In order to optimize the relocation parameters of No. 3 raw coal semi fixed crushing station in Shengli West No. 2 open-pit coal mine, the development of stope and waste dump engineering positions in each year is deduced through the preparation of the mining schedule, and then the appropriate relocation time node of No. 3 crushing station is analyzed and determined. Two methods of relocation cost compensation and weighted cost minimization are proposed to determine the economic and reasonable relocation step of No. 3 crushing station. The indexes such as raw coal resources, raw coal truck transportation distance, belt transportation distance and service life of the crushing station in the mining block are calculated and determined when the No. 3 crushing station is moved at different distances, and the reasonable moving distance of the No. 3 crushing station is calculated and determined. The research results show that the relocation time point of No. 3 crushing station is before April 2026, and the relocation path is to retreat along the layout direction of the belt transportation system at the east side of the stope, with a relocation distance of 1200 m. At this time, the relocation cost is compensated, the weighted cost is minimal, and the economic effect is good.