井筒基岩段过特殊地层井壁设计及施工优化

张乃宏1,王晓健2   

  1. 1. 皖北煤电朱集西煤矿
    2. 安徽理工大学土木建筑学院地下结构研究所
  • 收稿日期:2012-07-19 修回日期:2012-09-05 出版日期:2013-08-10 发布日期:2013-08-10
  • 通讯作者: 王晓健 E-mail:xjwangyhl@163.com

Shaft lining design and construction optimization in special formation through bedrock

  • Received:2012-07-19 Revised:2012-09-05 Online:2013-08-10 Published:2013-08-10

摘要: 基于朱集西煤矿风井井筒基岩段地质条件十分复杂,采用理论计算得出在该特殊地层中需要在井壁中配筋;研究了风井井壁结构的优化,调整了在特殊地层的井壁施工方案,结果表明井壁承载力得到提高,井筒顺利通过特殊地层。

关键词: 井壁, 特殊地层, 方案优化, 井筒安全

Abstract: Because the geological conditions in bedrock section of Zhu Ji Xi Coal Mine wind shaft is very complicated, reinforcement concrete in the shaft lining in the special formation in adopted through theory calculation; Air shaft lining structure is optimized and shaft lining construction program is adjusted in the special formation. The result is clear that lining bearing capacity is improved and shaft safety is ensured in special formation.

Key words: Shaft lining, Special formation, Program optimization, Shaft safety