Design of River Diversion Project and Application of Environmental Measures in Yuanbaoshan Open-cast Mine

  

  • Received:2013-08-09 Revised:2013-09-27 Online:2013-11-10 Published:2013-11-11

Abstract:

Firstly, based on the engineering background and necessity of the Yingjin river diversion project in Yuanbaoshan mine of Pingzhuang Coal Group LTD, this article calculates the parameters of river embankment, evaluates the safety of seepage control and stability, and then proposes the design scheme of the river diversion project. Secondly, through the analyze on the environmental factors influenced by the project, such as soil, vegetation and animals, the environmental measures are raised and carried out, which ensure the coordinated development of the mine.

Key words: Open-air coal mine, The river changes a way, Design, Environmental protection, measure, applied