煤炭工程 ›› 2014, Vol. 46 ›› Issue (2): 46-48.doi: 10.11799/ce201402016
• 生产技术 • 上一篇 下一篇
朱若军1,李志华2,杨科3
收稿日期:
修回日期:
出版日期:
发布日期:
通讯作者:
Received:
Revised:
Online:
Published:
摘要:
针对大倾角大采高倾斜长壁工作面综采设备安装速度慢、周期长等问题。刘庄煤矿通过在工作面轨道顺槽上部施工组装硐室,创造条件只采用一部无极绳绞车打运。提高了打运效率,实现了大倾角大采高倾斜长壁工作面的安全、经济、快速安装,只用42d 时间就安装完毕350m 超长大采高综采工作面。为类似条件综采工作面快速安装提供了宝贵经验。
关键词: 大采高, 大倾角, 倾斜长壁, 快速安装, 无极绳绞车
Abstract:
In order to solve the problem of fully mechanized mining equipment installation of inclined longwall face with large mining height and large inclined angle, the Liuzhuang Coal Mine disposes assembly chamber at the top of tail entry, which can create condition for use only a no terminal rope winch to satisfy auxiliary transportation. It improves transportation efficiency and realizes safe, economic and fast installation in inclined longwall face with large mining height and large inclined angle, this method only spend 42d for installation a 350m super-long and large mining height working face. It has great significance for fast installation with similarity condition.
Key words: large mining height, large inclined angle, inclined longwall mining, fast installation, no terminal rope winch
中图分类号:
TD 324
朱若军,李志华,杨科. 大倾角大采高倾斜长壁工作面快速安装技术[J]. 煤炭工程, 2014, 46(2): 46-48.
0 / / 推荐
导出引用管理器 EndNote|Reference Manager|ProCite|BibTeX|RefWorks
链接本文: http://www.coale.com.cn/CN/10.11799/ce201402016
http://www.coale.com.cn/CN/Y2014/V46/I2/46
[1] 周卫金,吴灿银,周卫星,等.大采高综采工作面快速安装技术[J].煤矿开采,2009,14(2):27-29. [2] 鲁军,张进忠,马立强.大倾角综采工作面设备快速安装技术[J].能源技术与管理,2011,(10):10-12. [3] 张传涛,王德玉.快速安装轻型综采支架方法的探讨[J].煤炭工程,2007,(1):35-36. [4] 张成义.浅谈综采工作面快速安装的实践[J].矿业工程,2010,8(3):30-31. [5] 楚乐献,吴文轶,张明华.综采工作面快速安装经验探析[J].煤炭工程,2005, (11):28-29. [6] 周耀光,陈清华,常聚才.煤矿井下柔性辅助运输系统设计与应用[J].煤矿开采,2011,16(4):46-47.