煤炭工程 ›› 2018, Vol. 50 ›› Issue (8): 1-6.doi: 10.11799/ce201808001

• 设计技术 • 上一篇    下一篇

南梁煤矿采留一体无掘巷开采技术应用研究

郑忠友,杨晓科,朱磊,等   

  1. 1.
    2. 中煤西安设计工程有限责任公司
    3. 中煤能源研究院有限责任公司
    4. 中煤西安设计工程公司
    5. 中煤西安设计工程有限责任公司矿井所
  • 收稿日期:2017-11-14 修回日期:2018-02-16 出版日期:2018-08-20 发布日期:2018-12-17
  • 通讯作者: 杨晓科 E-mail:yangxiaoke2005@163.com

Research on the Technique of Gob-side Retaining and Shearer cutting Tunnel mining System in Nanliang Coal Mine

  • Received:2017-11-14 Revised:2018-02-16 Online:2018-08-20 Published:2018-12-17

摘要: 为解决现阶段煤矿开采中留设区段保护煤柱资源浪费严重,因煤柱上方应力集中引起的巷道围岩变形严重,冲击地压、煤(岩)爆以及煤与瓦斯突出等地质灾害,提出采留一体无掘巷开采技术,论述了其技术原理和理论基础,研究了采割一体机成巷技术、切顶卸压成巷技术、切顶卸压锚体梁支护理论,并研发了适应于新技术的成套自动化设备。根据南梁煤矿的地质条件,给出了采留一体生产布置系统,包括巷道布置系统和辅助生产系统。通过数值模拟实验,得出了南梁煤矿切顶卸压留巷切缝高度,切缝角度等关键参数,通过理论分析与现场实验结合得到切缝钻孔布置、留巷支护等关键参数。现场工业性实验结果表明,采割一体机成巷效果良好,切顶卸压留巷保持稳定,与传统开采方式经济比较降本增效明显,为解决我国长壁工作面提供一种经济有效无煤柱、无掘巷开采新理论与技术。

关键词: 采留一体开采技术, 无掘巷, 切顶卸压, 沿空留巷, 无煤柱开采

Abstract: In order to solve the problem of coal processes of mining and tunneling particularly become unsmooth, to solve the disasters of the serious deformation of the surrounding rocks, the rock burst, the rock and coal burst, the coal and gas outburst by the stress concentration of the coal block coal pillar in the present stage coal mining system, we proposed the method of no-pillar and no tunneling mining with gob-side retaining and Shearer cutting Tunnel mining System. This essay introduced the principle and theoretical analysis of this new technique, and the shearer cutting Tunnel technique, the roof cutting and pressure relief technique, the overlying strata structure of roof cutting and anchor rope beam Supporting theory, and the workface special equipment are given. According to the geological condition of Nanliang coal mine, the product system of the new technique was given including tunnel arrangement system, subsidiary production system such as power supply system, transportation system, ventilation system, we were get the cutting heights and cutting angels of the roof by using FLAC3D numerical simulation software, according to the theoretical analysis and the field tests, get the key parameters of blasting hole intervals and gob-side entry retaining supporting. Through field industrial experiments the Technique of gob-side retaining and shearer cutting Tunnel mining system was succeed, the tunnel which shearer cut was effective, the gob-side retaining by roof cutting was stable. Through the economic analysis of this two mining methods, the new technique is concluded that the cost reduction and efficiency increase obviously, which provides a new economic and effective theory and technique for no-pillar and no tunneling mining in long wall face.

中图分类号: