煤炭工程 ›› 2020, Vol. 52 ›› Issue (1): 59-63.doi: 10.11799/ce202001013

• 施工技术 • 上一篇    下一篇

矿用小孔径预应力拉力分散型锚索锚固结构研究及应用

杨永刚,李琰庆   

  1. 1. 安徽省煤炭科学研究院
    2. 淮南矿业(集团)有限责任公司
  • 收稿日期:2018-11-22 修回日期:2019-02-15 出版日期:2020-01-10 发布日期:2020-05-13
  • 通讯作者: 杨永刚 E-mail:yyg0919@126.com

The Anchorage structure and application of small aperture prestressed tensile dispersion anchor cable for mine

  • Received:2018-11-22 Revised:2019-02-15 Online:2020-01-10 Published:2020-05-13

摘要: 采用数值模拟方法分析了目前煤矿小孔径树脂锚固锚索剪应力分布特征,指出其受力本质为拉力集中型,在外锚固起始段会产生严重的应力集中现象,容易造成锚索锚固段渐进破坏,进而导致锚索锚固失效。通过凝胶时间达6~8h、抗压强度60MPa以上缓凝型树脂锚固剂的研发,提出了矿用新型小孔径拉力分散型锚索结构及施工工艺。在现有矿用锚索支护施工工艺不变的条件下,实现了同一钻孔内不同锚固段树脂药卷的分时分段锚固。数值计算结果表明矿用拉力分散型锚索能够将锚固段剪应力分散至两处,显著降低锚固段应力集中程度。工程应用结果表明,该技术能够大幅提高锚索内锚可靠性及锚索强度利用率,有效改善锚索内锚力与破断力的匹配性能,对巷道变形控制效果显著。

关键词: 小孔径, 预应力, 拉力分散型锚索, 锚索锚固结构, 缓凝型树脂锚固剂

Abstract: The anchorage structure and force characteristics of small aperture resin anchorage cable in coal mine are analyzed. The anchorage force lower than its breaking force caused by the unreasonable anchorage structure about tension concentration type anchor cable is one of important reasons why it is difficult to control the deformation of rock surrounding in deep roadway, and this objective fact was pointed out. The anchor structure is comprehensive analyzed, one is anchor cable by tension concentration type for mining, another is anchor cable by tension dispersion type which commonly used in geotechnical engineering. The resin anchorage agent with slow condensation is developed which gel time 6 ~ 8h and pressure strength 60 MPa or more. On that basis ,the structure and construction technology of a new type of small aperture tensile dispersion anchor cable for mining are presented. Under the construction technology of anchor cable used for mining unchanged condition, time-division anchoring of resin coil with different anchorage sections in the same hole is realized. The anchor section shear stress of the anchor cable is dispersed to two places, and stress concentration in anchorage section is reduced. The application results of multi-pair mine engineering show that this technique can greatly improve anchor reliability and strength utilization of anchor cable. The matching performance of anchorage and breakage in anchor cables are improved, and the control effect of roadway deformation is enhanced significantly.

中图分类号: