煤炭工程 ›› 2023, Vol. 55 ›› Issue (7): 1-6.doi: 10.11799/ce202307001

• 设计技术 •    下一篇

近距离煤层变层间距开采下位煤层巷道合理位置研究

刘晓明,李铁峥,雷学涛,黄海鹏,李 杨,任玉琦,王文迪   

  1. 1. 国家能源集团宁夏煤业有限责任公司 梅花井煤矿,银川 宁夏 751400
    2. 中国矿业大学(北京) 能源与矿业学院,北京 100083

  • 收稿日期:2023-03-22 修回日期:2023-06-05 出版日期:2023-07-20 发布日期:2025-04-07
  • 通讯作者: 李铁峥 E-mail:zqt2100102070@student.cumtb.edu.cn

Study on the optimum location for entry in lower coal seam with variable spacing in Meihuajing coal mine

  • Received:2023-03-22 Revised:2023-06-05 Online:2023-07-20 Published:2025-04-07

摘要:

为确定宁夏梅花井煤矿近距离煤层变层间距开采条件下位3 号煤层巷道的合理位置,结合上位2 号煤层232204 工作面与下位3 号煤层的5 组层间钻孔信息, 通过理论分析、现场实测与数值模拟的方法, 探究了上位2 号煤层开采后底板煤岩层的破坏范围, 分析了上位煤层开采后底板煤岩层的裂隙发育规律与应力分布规律特征, 确定了下位3 号煤层工作面回采巷道的合理位置。研究结果表明: 依据5 组层间钻孔信息计算得出底板煤岩层的最大破坏深度为19. 57 m, 下位3 号煤层基本受到上位2 号煤层开采的扰动破坏; 变层间距条件下裂隙发育区域呈倒梯形, 且应力降低区与边界煤柱的最大水平距离为9. 69 m; 考虑1. 5 倍的安全系数, 最终确定了下位煤层回采巷道需内错15 m 布置, 并提出了变层间距条件下巷道分区支护方案。

关键词: 近距离煤层, 变层间距, 底板破坏, 巷道布置

Abstract:

In order to determine the optimum location for entry of the lower No. 3 coal seam with the variable seam spacing and close coal seams of Meihuajing coal mine in Ningxia, by combining the 5 interlayer boreholes information of the lower No. 3 coal seam and the 232204 panel face in the upper No. 2 coal seam, the failure range of the floor after the upper No. 2 coal seam mining is explored through theoretical analysis, field monitoring and numerical simulation. The fracture development regularity and stress distribution characteristics of the floor with information of 5 interlayer boreholes after the upper coal seam mining are analyzed, and the optimum location for entry is determined. The main conclusions are as follows: 1) the maximum failure depth of the floor with information of 5 interlayer boreholes is 19.57 m and the lower No. 3 coal seam is basically disturbed by the mining of the upper No. 2 coal seam. 2) the inverted trapezoidal zone appears in the fracture development areas with variable spacing mining, and the maximum horizontal distance between the stress-relaxation area and boundary pillar is 9.69 m. 3) The entry of lower coal seam is arranged with an inner stagger distance of 15 m considering a 1.5 safety factor and a scheme of partition entry support under variable layer spacing conditions is proposed. The results can provide a reference for the layout of entry with similar conditions.