煤炭工程 ›› 2021, Vol. 53 ›› Issue (11): 108-112.doi: 10.11799/ce202111021

• 研究探讨 • 上一篇    下一篇

注浆加固深度对底板岩层变形影响分析

李见波,尹尚先, 王钢   

  1. 1. 华北科技学院 安全工程学院, 河北 三河 065201
    2. 鄂尔多斯市国源矿业开发有限责任公司, 内蒙古 鄂尔多斯 010300
    3. 华北科技学院 河北省矿井灾害防治重点实验室, 河北 三河 065201
  • 收稿日期:2021-02-21 修回日期:2021-03-31 出版日期:2021-11-20 发布日期:2022-01-05
  • 通讯作者: 李见波 E-mail:lijbo@126.com

Analysis of the influence of grouting reinforcement depth on the deformation of floor strata

  • Received:2021-02-21 Revised:2021-03-31 Online:2021-11-20 Published:2022-01-05

摘要:

为了更好地进行底板注浆加固设计, 开展了近奥灰特条件下加固深度对底板岩体变形影响研究。结合矿井地质条件构建了采动作用下奥灰顶部风化岩层影响下底板岩层的基本形态, 分析了注浆加固对不同层位岩层的作用效果。建立数值模型进行验证。计算结果表明, 奥灰顶部岩层被风化时, 岩层变形在垂向上存在明显的突变点, 布置监测点的位移曲线在形态表现为三段。当设计底板加固深度14m时监测点位移值小于岩体不加固时的位移值, 位移减小6.2%; 当设计加固奥灰顶部风化岩层时, 位移值小于设计加固深度14m时位移值, 且位移减小明显。开采见方时所有监测点位移曲线分为三段型和两段型, 随着加固深度增加, 三段型向两段型转变, 一定程度上注浆加固深度越大注浆效果越好。

关键词: 特厚煤层, 岩体破坏, 注浆设计, 奥灰岩, 风化岩层

Abstract:

In order to study the influence of reinforcement depth on the deformation and failure of floor rock for the grouting design, the influence of reinforcement depth on the deformation and failure of floor rock under the condition of near Ordovician limestone confined aquifer and thin aquiclude is studied. According to the geological conditions of the mine, the basic shape of the floor rock under the influence of the weathering zone under the mining action is constructed, and the effect of grouting reinforcement on different strata is analyzed. Then, the numerical model is established for verification. The calculation results show that there are obvious mutation points in the displacement curve of the monitoring points when the top layer of Ordovician limestone is weathered. The displacement curve of the monitoring points is divided into three sections, corresponding to the weathered rock, Ordovician limestone and the upper floor rock of the weathered layer. The maximum displacement of the monitoring point with the reinforcement depth of 14 m is less than the maximum displacement of the rock mass without reinforcement, and the displacement decreases by 6.2%; when the weathered rock mass on the top of Ordovician limestone is reinforced, the maximum displacement is less than the maximum displacement with the reinforcement depth of 14m, and the displacement decreases obviously. The displacement curve of monitoring points can be divided into three sections and two sections with mining length of 250 m; with the increase of reinforcement depth, the three sections change to two sections. Grouting reinforcement plays a good role in resisting the deformation of the floor. To a certain extent, the greater the depth of grouting reinforcement, the better the grouting effect.

中图分类号: