煤炭工程 ›› 2020, Vol. 52 ›› Issue (7): 68-73.doi: 10.11799/ce202007016

• 生产技术 • 上一篇    下一篇

综放开采多煤柱扰动致冲危险性分析及监测防控技术

吴波   

  1. 中国中煤能源集团有限公司
  • 收稿日期:2020-02-28 修回日期:2020-05-26 出版日期:2020-07-15 发布日期:2020-08-21
  • 通讯作者: 吴波 E-mail:wubo@chinacoal.com

Disturbance risk analysis and monitoring and control technology of multi-pillars in fully mechanized caving mining

  • Received:2020-02-28 Revised:2020-05-26 Online:2020-07-15 Published:2020-08-21

摘要: 为研究综放开采多煤柱扰动造成冲击地压的危险性,以担水沟矿9203工作面煤柱实际分布情况为工程背景,基于极限平衡理论和应力扰动影响角,建立了侧向区段煤柱、上覆遗留区段煤柱和终采线煤柱的应力扰动计算模型,获得了不同类型煤柱的扰动致冲危险区域,并提出应用煤体应力、微震监测及钻屑检验预警配合钻孔卸压为主的多煤柱扰动防冲和监测预警技术。结果表明:侧向区段、上覆遗留区段、上覆终采线及侧向终采线煤柱的扰动致冲危险区域分别为所扰动巷道两帮7.2m浅部区域、沿采场倾斜方向区段煤柱至采场端头以里39.8m区域、上覆终采线至采空区深部47m区域及侧向终采线起点至本工作面终采线范围内的侧向区段煤柱和采场端部区域|现场采取监测预警防控技术后,未监测到应力及微震预警事件,应用效果良好。

关键词: 综放开采, 区段煤柱, 冲击地压, 应力扰动, 微震监测

Abstract: In order to study the rock burst risk caused by the disturbance of multiple coal pillars in full-mechanized caving mining, the stress disturbance calculation models of lateral section coal pillar, overlying remnant coal pillar and the coal pillar of stopping line were built respectively by using the limit equilibrium theory and stress disturbance angle, which were based on the actual distribution of coal pillars of 9203 working face in Danshuigou mine. The disturbance dangerous areas of the different coal pillars were obtained. And the control and early warning technologies of rock burst under the disturbance of multi-pillars were provided, which mainly included the pressure relief technology of boreholes and the monitoring technology of the coal stresses, micro-seismic events and drilling cuttings inspection. The results show that the disturbance dangerous areas of lateral section coal pillar, overlying remnant coal pillar, the coal pillar of overlying and lateral stopping line are respectively the areas from the roadway’s sides to the 7.2m deeper, from the lateral section coal pillar to the 39.8m deeper of working face end along the dip direction of working face, from the overlying stopping line to the 47m deeper of gob, and the areas of the lateral section coal pillar and working face end form the start points of the lateral stopping line to the stopping line of mining working face. After the control and early warning technologies applied, there were no the early warning of stresses and micro-seismic events in the field, and it had a good application effect.

中图分类号: