煤炭工程 ›› 2022, Vol. 54 ›› Issue (8): 12-16.doi: 10.11799/ce202208003

• 设计技术 • 上一篇    下一篇

采区主运输巷局部二次挑顶立交过巷改造方案设计

刘光金1,于健浩2   

  1. 1. 宁夏煤矿设计研究院有限责任公司
    2. 中煤科工开采研究院有限公司
  • 收稿日期:2022-01-04 修回日期:2022-04-20 出版日期:2022-08-15 发布日期:2022-09-06
  • 通讯作者: 于健浩 E-mail:yujh620@126.com

Analysis on the reconstruction scheme the local secondary construction of belt haulage roadway across the roadway

  • Received:2022-01-04 Revised:2022-04-20 Online:2022-08-15 Published:2022-09-06

摘要: 煤矿主、辅运系统在设计过程中难免出现同层位交叉布置,传统解决方案为布置绕道,但存在施工周期长、工程量大、投资高等诸多问题,以宽沟煤矿接续采区井底车场主运输石门和轨道大巷为研究背景,提出了轨道巷绕行、主运输巷局部挑顶抬高立交两种交叉布置解决方案。采用理论计算、数值模拟方法,分析了带式输送机曲线段运输能力,校验了交叉点巷道支护参数。从工期、投资及运营费用等方面对两方案进行了比较,主运输巷挑顶立交方案相比于轨道巷绕行方案而言,系统简单、工期短、投资少、运营费用低,最终确定选用主运输石门挑顶立交方案,并进行了现场实施,取得了良好的技术经济效益。

关键词: 主运输巷道, 二次挑顶, 带式输送机, 局部挑高, 立交布置

Abstract: At present, the coal transportation (main transportation) in underground laneways of coal mines in our country mostly adopts the transportation mode of belt conveyor, personnel, equipment, materials, gangue and other auxiliary transport using trackless rubber-tyred vehicles, traditional rail plus aerial vehicle, monorail crane, rail truck and other ways. The main and auxiliary transportation systems inevitably need to cross over, and the general treatment plan is to raise the main transportation roadway (belt roadway) as a whole to achieve a certain height of roadway cross-layout, but in the course of the connection of Kuanggou Coal Mining area, in the past, the construction of main and auxiliary haulage roadways in the first mining area has been completed at the same elevation without crossing, so it is very difficult to arrange the roadways crossing. When the author demonstrates the continuous mining area of Kuangou Coal Mine, the position of the track system in the underground car park needs to be extended from one side of the stone gate to the other side, two schemes are put forward, one is the track roadway around, the other is the belt roadway with local roof-lifting. In view of the proposed interchange scheme, firstly, the possibility of equipment transformation is calculated and analyzed, and it is determined that the belt conveyor can meet the transportation demand of roadway curve section after technical transformation Then, the support form and parameter optimization scheme of the cross-point roadway is put forward by using FLAC software, which ensures the safety and stability of the roadway surrounding rock. Through the detailed comparison of the construction period, investment and operation cost of the two schemes of the track lane bypass and the belt lane local lifting the roof, etc. , the scheme of belt laneway overhead crossing is simpler than that of track laneway around, the construction period is shorter, the investment is less, and the operation cost is lower, good technical and economic benefits have been obtained. The case of the Roadway interchange can be used as a reference for technicians in the similar layout of the existing roadway system.

中图分类号: