煤炭工程 ›› 2023, Vol. 55 ›› Issue (3): 127-132.doi: 10.11799/ce202303023

• 研究探讨 • 上一篇    下一篇

基于COMSOL的顶板定向长钻孔布置参数研究

姜周民   

  1. 中国矿业大学(北京)
  • 收稿日期:2022-06-21 修回日期:2022-10-19 出版日期:2023-03-20 发布日期:2023-04-11
  • 通讯作者: 崔俊启 E-mail:3040396945@qq.com

Study on Layout Parameters of Long Directional Boreholes in Roof Based on COMSOL

  • Received:2022-06-21 Revised:2022-10-19 Online:2023-03-20 Published:2023-04-11

摘要: 为了研究顶板定向长钻孔的布孔参数,以东庞矿21215工作面为工程背景,通过利用COMSOL数值模拟软件,建立了5种不同布置方式下顶板长钻孔的瓦斯抽采模型,根据模拟结果确定了“法向间距2 m、水平间距3 m”的钻孔布置方式。根据21215工作面裂隙带高度设计了钻孔的布置参数,同时利用钻孔水平位置理论确定公式验证了布孔参数的可行性。现场应用结果表明,工作面回采过程中顶板定向长钻孔抽采存在稳定阶段和衰减阶段,在衰减阶段钻孔抽采效果降低、上隅角瓦斯浓度提高,分析其原因是由于钻孔高度降低,钻孔完整性遭到破坏导致的。从整体来看,在回采期间上隅角瓦斯浓度为0.3%~0.4%,处于较低水平,说明顶板定向钻孔抽采效果较好,采用该布置方式有效解决了上隅角瓦斯浓度超限的问题。

关键词: 定向长钻孔, 钻孔布置方式, 钻孔布置参数, 上隅角, 抽采效果

Abstract: In view of the deficiency that the current research on the hole layout parameters of roof directional long drilling is only to determine the drilling layout horizon and horizontal range, taking the 21215 working face of Dongpang mine as the engineering background, the vas pumping model of roof long drilling under five different layout modes is established by using COMSOL numerical simulation software, and the drilling layout mode of "normal spacing of 2 m and horizontal spacing of 3 m" is determined according to the simulation results. According to the height of fracture zone in 21215 working face, the layout parameters of drilling holes are designed, and the feasibility of hole layout parameters is verified by using the formula determined by the horizontal position theory of drilling holes. The field application results show that in the mining process of the working face, there are stable stage and attenuation stage in the roof directional long drilling drainage. In the attenuation stage, the drilling drainage effect decreases and the gas concentration in the upper corner increases. The analysis is due to the reduction of the drilling height and the destruction of the drilling integrity. On the whole, the gas concentration in the upper corner during mining is 0.3% ~ 0.4%, which is at a low level, indicating that the drainage effect of roof directional drilling is good. This arrangement effectively solves the problem of gas concentration overrun in the upper corner.

中图分类号: